Prevention, Waiver and Estoppel in the Employer’s Conduct: UKGH v DHSC

12 March 2026

A recent decision of the Technology and Construction Court in UK Global Healthcare Ltd v Secretary of State for Health and Social Care [2026] EWHC 561 (TCC) highlights an important point that frequently arises in commercial and construction disputes: a party may be prevented from insisting upon strict compliance with contractual deadlines where its own conduct has arguably prevented performance.

The case arose out of contracts entered into during the early stages of the COVID-19 pandemic for the supply of medical gloves to the NHS. The judgment provides a useful illustration of how waiver, estoppel and the prevention principle may affect the enforcement of contractual deadlines, even where the contract contains strict “time of the essence”, “no waiver” and “no oral modification” provisions.

Background

In May and June 2020, the Department of Health and Social Care (“DHSC”) entered into two contracts with UK Global Healthcare Ltd (“UKGH”) for the supply of approximately 320 million nitrile examination gloves. The contracts required delivery in phases, with the first deliveries due by 30 June 2020. The contracts also expressly provided that time was of the essence, meaning that failure to meet the delivery dates would constitute a material breach.

Under the payment structure, DHSC paid £15.35 million upfront to UKGH. However, the gloves were never delivered. DHSC subsequently terminated the contracts and sought repayment of the advance payments. UKGH, on the other hand, contended that the failure to deliver had been caused by DHSC’s own conduct during the procurement process.

The Dispute

The core dispute centred on additional testing and inspection requirements that arose after the contracts had already been signed. Shortly after entering into the contracts, DHSC requested further testing of the gloves, including laboratory testing to specific international standards. According to UKGH, these requirements were not part of the contractual specification, particularly in respect of the initial deliveries due by the end of June 2020. UKGH complied with the requests but warned that the additional testing would delay the delivery programme.

Correspondence between the parties indicated that the delivery dates would likely need to be varied to accommodate the additional testing process. In late June 2020, DHSC acknowledged in correspondence that it “made total sense” to amend the delivery dates to allow for further assurance regarding the quality of the gloves. Testing later carried out by a UK laboratory suggested that the gloves failed certain standards, and DHSC informed UKGH that the gloves would not be accepted. The contracts were purportedly terminated by DHSC in October 2020. DHSC then sought repayment of the advance payments on the basis that the gloves had never been delivered.

The Court Proceedings

DHSC applied to the court for summary judgment, arguing that the supplier had plainly failed to meet the contractual delivery deadlines and that the contracts entitled DHSC to recover the advance payments. UKGH resisted the application and argued that the case required a full trial because DHSC’s conduct had effectively prevented the deliveries from occurring within the contractual timeframe. The Court therefore had to determine whether UKGH’s arguments had a real prospect of success, or whether DHSC was entitled to summary judgment on its counterclaim.

The Court’s Analysis

The court refused to grant summary judgment. The key issue was whether DHSC’s conduct during the testing process had affected the contractual delivery obligations. The judge noted several important points. First, the contracts did not clearly provide DHSC with a contractual right to require the additional pre-delivery testing that it had requested, particularly in relation to the initial deliveries due at the end of June 2020. Second, the contemporaneous correspondence between the parties suggested that both sides recognised that the additional testing would delay delivery and that new delivery dates would need to be agreed. Third, UKGH had accomodated DHSC’s requests on the understanding that the delivery dates would be extended to reflect the additional testing requirements. On the evidence before the court, there was therefore a real prospect that UKGH could establish at trial that:

  • DHSC had waived strict compliance with the original delivery dates, or
  • DHSC was estopped from relying on those dates, or
  • DHSC’s conduct had prevented performance, thereby engaging the prevention principle.

If UKGH succeeded on those arguments at trial, they could materially affect DHSC’s entitlement to rely on the original delivery dates and the validity of its termination and repayment claim.

The Prevention Principle

A further argument raised by UKGH relied upon the well-known prevention principle, which provides that a party cannot insist upon performance of a contractual obligation where that party has itself prevented performance. The Court accepted that there was at least a triable issue that DHSC’s additional testing requirements may have made it impossible for UKGH to meet the original delivery dates. In those circumstances, the delivery deadlines might no longer be enforceable in the way DHSC asserted.

Repayment of the Advance Payment

DHSC also relied on a contractual clause requiring UKGH to repay advance payments for goods that had not been delivered before termination or expiry of the contract. However, the Court held that there was a realistic argument that the clause could not be interpreted so as to allow DHSC to recover the advance payment if DHSC’s own conduct had caused the non-delivery. Applying the principle that a contract should not ordinarily be interpreted so as to permit a party to benefit from its own breach, the Court concluded that this issue also required determination at trial.

Decision

The Court therefore dismissed DHSC’s application for summary judgment. UKGH’s claim was permitted to proceed, with the issues of waiver, estoppel, prevention and termination left for determination at trial

Practical Implications

Although this dispute arose in the context of pandemic procurement, the decision contains lessons that are highly relevant to construction and engineering contracts. In practice, projects often involve requests for additional testing, inspections, approvals or documentation that may fall outside, or go beyond, the requirements originally contemplated by the contract. Where those requests affect the contractor’s ability to meet programme milestones, the employer may inadvertently create arguments based on waiver, estoppel or prevention. This case demonstrates that even where a contract contains:

  • strict “time of the essence” provisions;
  • no oral modification clauses; and
  • no waiver clauses,

the conduct of the parties during performance can still affect how those provisions operate in practice. The judgment also reinforces the importance of clearly documenting any changes to delivery dates, inspection requirements or programme obligations before they begin to affect contractual performance.

How CCC Can Help

Disputes concerning delay, variation, loss and expense, defects, termination, repudiation, payment recovery, retention and contractual interpretation are common across construction and engineering projects. Our team regularly assists contractors, subcontractors and employers in analysing contractual obligations, assessing entitlement to extensions of time and defending or pursuing claims arising from alleged breach of contract. If you are dealing with issues involving termination, delays, disputed testing requirements or payment recovery, early legal and commercial advice can be critical in protecting your position and avoiding costly disputes.

 

Contact us for a free initial consultation.

This entry was posted in News. Bookmark the permalink.

Get in touch





Related Insights

Common Causes of Construction Disputes and How to Avoid Them

Common Causes of Construction Disputes and How to Avoid Them

Why are disputes so common in construction? A job can start before the design is complete, involve input from several parties whose work depends on …

Read more
Advance Payments in Construction: Getting the Arrangements Right

Advance Payments in Construction: Getting the Arrangements Right

Be clear about what the payment is funding An advance towards a specific equipment order serves a different purpose from a payment intended to support …

Read more
Novation or Assignment? Why the Difference Matters in Construction Contracts

Novation or Assignment? Why the Difference Matters in Construction Contracts

Assignment and novation provisions are not usually the first clauses contractors or subcontractors focus on when reviewing a construction contract. But if a project changes …

Read more

Sign up for Legal Tips & Events