Assignment and novation provisions are not usually the first clauses contractors or subcontractors focus on when reviewing a construction contract. But if a project changes hands, a consultant is transferred to a new client, a company restructures or contractual rights are passed to somebody else, assignment and novation provisions can suddenly become very important. The distinction affects what has actually transferred, who remains responsible for the contractual obligations and, crucially, who can pursue whom if something goes wrong.
The basic difference is relatively simple:
- Assignment generally transfers contractual rights or benefits.
- Novation can replace one contracting party with another, so that the contractual relationship itself moves to the incoming party.
The practical consequences can be much less simple.
Assignment: what moves and what stays behind?
An assignment generally transfers the benefit of contractual rights and it does not ordinarily transfer the burden. For example, an employer might assign rights under a building contract to a purchaser or funder. If Party A owes money or has other contractual obligations to Party B, Party A cannot generally make Party C responsible for those obligations simply by assigning its contractual rights to Party C. The original contracting party therefore remains important even after an assignment has taken place. That can be important if a dispute arises.
The contract also needs to be checked before any assignment is made. Construction contracts frequently contain provisions restricting assignment, requiring consent or permitting assignment only in particular circumstances. Any relevant notice requirements and formalities also need to be dealt with correctly. The important point is that an assignment should not be treated simply as an administrative change of name. You need to understand what rights are being transferred and what obligations remain where they were.
Novation: when a new party steps into the contract
Novation goes further. It is generally used where the intention is to substitute one contracting party with another. That requires the agreement of the parties involved, including the incoming party. That agreement may be captured as an obligation in a construction contract.
A familiar example is the novation of a design consultant. In that example an architect or engineer may initially be appointed by the employer during the design stage. Once a design and build contractor is appointed, that consultant may then be novated so that it continues providing its services to the contractor. At first sight, that can look straightforward as the consultant has simply moved from one client to another. But the wording of the novation agreement is important. In particular:
- Who has the benefit of rights arising from work carried out before the novation?
- Who is responsible for breaches or design issues arising from earlier services?
- Is the outgoing party released from future obligations?
- What rights does the incoming party acquire in respect of the consultant’s previous work?
These issues cannot safely be answered simply by saying that the appointment has been “novated”. The actual terms of the novation need to be checked.
Why does it matter?
The consequences were demonstrated in Grove Construction (London) Ltd v Bagshot Manor Ltd [2025] EWHC 591 (TCC). Grove had carried out refurbishment works under a contract with Bagshot Manor Developments Ltd (“BMDL”). Following practical completion, Grove was due retention. BMDL subsequently entered administration and its rights under the building contract were assigned to Bagshot Manor Ltd. Grove then sought to recover the unpaid retention from Bagshot and referred the dispute to adjudication. The difficulty was that there had been an assignment, not a novation. Bagshot had acquired contractual rights, but it had not assumed BMDL’s obligation to pay Grove the retention. The Court therefore refused to enforce the adjudicator’s decision against Bagshot. The case illustrates an important point. The fact that a company has acquired rights under a construction contract does not automatically make it responsible for the original contracting party’s liabilities.
Does an assignee have adjudication rights?
There is an important distinction here. Grove does not mean that an assignee can never use adjudication. In Paragon Group Ltd v FK Facades Ltd [2026] EWHC 78 (TCC), the Court confirmed that an assignee of contractual rights could refer a dispute to adjudication against the original contractor. In that case the contractor was trying to make the assignee responsible for an obligation which had not transferred to it. The assignee was seeking to enforce rights which had been assigned to it against the contractor that remained bound by the original contract. So an assignment may transfer rights and the remedies available to enforce them. It does not, however, simply turn the assignee into the original contracting party for every purpose.
What should you check in your contract?
- Can the contract be assigned?
Some contracts permit assignment freely, while others require prior written consent or restrict the circumstances in which it can take place. - Can you be required to accept a novation?
Some contracts anticipate future novation or require parties to enter into particular transfer arrangements. - Who could your contract end up being with?
This can matter where the financial standing or commercial relationship with the contracting party was important when the price and risk were agreed. - What happens to existing rights and liabilities?
This is particularly important where a novation takes place part-way through a project or where design services have already been performed. - Who would you pursue if something went wrong?
Do not assume that the party now involved with the project has automatically inherited every obligation under the original contract.
If you are asked to sign a novation
Do not look only at the fact that the commercial relationship is changing. Check what the document actually does. If you are the incoming party, consider what existing rights and liabilities you are taking on. If you are the outgoing party, establish whether you are genuinely being released from future obligations and what happens to liabilities arising from events before the novation. If a consultant is being novated, particular attention should be paid to responsibility for design or other services already carried out.
If a contract has been assigned
Start with both the original contract and the assignment.
Establish:
- whether the original contract permitted the assignment;
- whether any required consent or notice was given;
- what rights were actually transferred;
- whether the claim you are dealing with falls within those rights; and
- which party remains responsible for the corresponding contractual obligations.
The key takeaway
Novation and assignment are relatively easy concepts to overlook when attention is focused on the more immediate commercial provisions of a construction contract. Most of the time, that may cause no difficulty. But if the project structure changes later, the distinction can suddenly determine who holds the contractual rights, who remains liable and who can bring or face a claim.
How CCC can help
Contract & Construction Consultants (CCC) advises employers, contractors, subcontractors and consultants on construction contract terms and project risk. We can review assignment and novation provisions as part of a wider contract review, advise where a transfer is proposed and help establish the contractual position where a project or contracting structure has already changed. Where a dispute has arisen, we can also review the original contract and transfer documentation to establish who holds the relevant rights, who remains responsible for the obligations and what options are available.