Advance Payments in Construction: Getting the Arrangements Right

12 October 2026

Be clear about what the payment is funding

An advance towards a specific equipment order serves a different purpose from a payment intended to support working capital throughout the project. The terms should reflect that distinction.

The agreement should identify any conditions attached to the payment, such as evidence that an order has been placed or a supplier deposit paid. If the money is intended for a particular purchase, agree how its use will be demonstrated.

For the recipient, those conditions should be workable. A requirement to prove that a supplier has already been paid before the advance is released may defeat the purpose if the advance is needed to fund that payment.

Match the protection to the risk

The paying party needs to consider what happens if the recipient or its supplier fails before the materials are delivered or the work is carried out.

Depending on the arrangement, protection might include an advance payment bond, direct payment to a supplier or provisions dealing with ownership of identified materials. Each requires careful consideration.

For materials held off site, practical questions include:

  • Have the goods been manufactured and clearly identified for the project?
  • Where are they stored, and are they insured?
  • What do the supplier’s terms say about ownership?
  • What rights would the paying party have to inspect or collect them?

Any security should also fit the payment arrangement. Check its amount, expiry date and conditions for reduction or release against the period during which the advance remains outstanding.

Agree when and how the advance will be recovered

Recovery terms can have a substantial effect on project cash flow.

An advance might be recovered through deductions from monthly payments, when particular materials are incorporated into the works or at an agreed later stage. The agreement should specify the mechanism and explain how it will appear in applications and certificates.

Both parties should work through the effect on anticipated payments. For example, recovering a £100,000 advance through deductions of £25,000 from each of the next four monthly payments could leave the recipient short of funds while it is still meeting substantial labour and procurement costs.

The terms should also address what happens if the project is delayed, an order is cancelled or the contract ends before recovery is complete.

A recent example: Westgreen v Kiryukhina

In Westgreen Construction Ltd v Kiryukhina [2026] EWHC 2189 (TCC), the contractor received advance payments totalling £650,000 under an amended JCT contract. Reimbursement was tied to specified events, including agreement and payment of the final account.

The Contract Administrator sought agreement to recover the money earlier through interim certificates, but Westgreen refused. A later certificate nevertheless removed the advances from the gross valuation while retaining them within previous certified amounts, effectively recovering the money.

Westgreen successfully challenged that in adjudication. The Court enforced the outstanding £650,000 award and refused to delay enforcement, noting that the contractual reimbursement conditions had not occurred.

The practical lesson is to check the agreed recovery terms before making deductions. If the arrangement needs to change, agree and document the amendment.

Keep the payment records clear

Applications and certificates should show the original advance, amounts recovered and the remaining balance clearly enough for both parties to reconcile them.

Care is needed where valuations are cumulative. Changing the treatment of an advance within the gross valuation can recover money without a separately identified deduction. Equally, including materials in a valuation without accounting properly for an advance can result in double counting.

An unexpected movement in the amount due should prompt a check of both the calculation and the contractual basis for recovery.

Check the arrangements through the supply chain

A contractor receiving an advance from an employer and making one to a subcontractor should compare the two arrangements.

If the employer starts recovering its advance before the contractor can recover the corresponding subcontract payment, the contractor may have to fund the difference. Similar issues can arise between subcontractors and their suppliers.

The amounts, payment dates, recovery terms and security requirements do not have to be identical, but any differences need to be understood and allowed for in the project’s cash flow.

How CCC can help

CCC assists employers, contractors and subcontractors with contractual payment arrangements and payment disputes. We can help review proposed advance payment terms, assess their commercial implications and advise where recovery is disputed.

Contact us for a free initial consultation.

This entry was posted in News. Bookmark the permalink.

Get in touch





Related Insights

Common Causes of Construction Disputes and How to Avoid Them

Common Causes of Construction Disputes and How to Avoid Them

Why are disputes so common in construction? A job can start before the design is complete, involve input from several parties whose work depends on …

Read more
Novation or Assignment? Why the Difference Matters in Construction Contracts

Novation or Assignment? Why the Difference Matters in Construction Contracts

Assignment and novation provisions are not usually the first clauses contractors or subcontractors focus on when reviewing a construction contract. But if a project changes …

Read more
Delay and termination: When does delay become repudiatory? Lessons from Durkan v Wallace

Delay and termination: When does delay become repudiatory? Lessons from Durkan v Wallace

Delay can put enormous commercial pressure on a construction project. But even significant delay does not automatically give a party the right to terminate. The …

Read more

Sign up for Legal Tips & Events