TCC strengthens the reach of the Building Safety Act: Crest v Ardmore

1 April 2026

The Technology and Construction Court has handed down another significant decision concerning the expanding scope of the Building Safety Act 2022 in Crest Nicholson Regeneration Ltd & Ors v Ardmore Construction Ltd & Ors [2026] EWHC 789 (TCC). The judgment follows the earlier substantive decision in which the Court granted both an anticipatory Building Liability Order (“BLO”) and an Adjudication BLO against associated Ardmore group companies.

The decision is important for contractors, developers, group companies and insolvency practitioners alike, as it continues the judicial trend of interpreting the Building Safety Act broadly in order to maximise routes of recovery for parties facing historic building safety defects.

Background to the Dispute

The underlying dispute arose from an adjudicator’s decision requiring Ardmore Construction Limited (“Ardmore”), the First Defendant, to pay Crest Nicholson Regeneration Ltd and associated Crest group companies (together, “Crest”) approximately £14.9 million. Ardmore subsequently entered administration, and Crest sought Building Liability Orders (“BLOs”) under section 130 of the Building Safety Act 2022 against several associated Ardmore entities.

Ardmore was the design and build contractor responsible for the development and the entity against which the underlying defects claims and adjudication liability arose. Other parties were also joined as defendants to the wider proceedings (together, the “Defendants”).

The Fourth to Tenth Defendants were associated companies within the Ardmore group against which Crest sought the BLOs (the “BLO Defendants”). Although the BLO Defendants were not themselves the original contracting party, the Court concluded in the earlier judgment that it was just and equitable for Ardmore’s relevant liabilities to be imposed on them on a joint and several basis.

The present judgment addressed consequential matters, including permission to appeal, a stay of execution, time to pay, interest and costs.

Adjudicators’ Awards can constitute a “Relevant Liability”

One of the most significant aspects of the decision is the Court’s confirmation that an adjudicator’s award can constitute a “relevant liability” for the purposes of the Building Safety Act. The BLO Defendants argued that adjudication decisions are only temporarily binding and should therefore fall outside the statutory regime. The Court rejected that argument, holding that an adjudicator’s decision gives rise to a present legal liability capable of being extended to associated companies through a BLO.

The judgment is an important development in the relationship between adjudication enforcement and the Building Safety Act. In practical terms, it reinforces that the “pay now, argue later” principle underpinning adjudication is not displaced merely because the original contracting entity is insolvent or financially distressed, where associated entities may properly fall within the scope of the Act.

Anticipatory Building Liability Orders Remain Available

The Court also reaffirmed that anticipatory BLOs are permissible. The Defendants argued that the Court should not make BLOs before final determination of liability and quantum at trial. However, the Court held that such an interpretation would significantly undermine the purpose of the legislation.

The Building Safety Act was intended to provide effective recovery mechanisms against associated entities responsible for historical building safety defects, and the Court considered that restricting BLOs only to finally determined liabilities would frustrate that purpose.

Stay of Execution Refused

The judgment further demonstrates the Court’s continued robust approach to applications seeking to resist enforcement of adjudications. The BLO Defendants sought a stay of execution and additional time to pay, asserting financial difficulties and potential insolvency consequences.

The Court was highly critical of the financial evidence advanced, identifying inconsistencies in cash flow forecasts, property valuations and funding arrangements. Ultimately, the Court concluded that the Defendants had failed to demonstrate any genuine inability to pay.

Importantly, the Court reiterated established TCC enforcement principles that financial difficulty alone will rarely justify a stay of execution. The judgment reinforces the longstanding position that successful parties in adjudication should generally not be deprived of the immediate benefit of enforcement absent truly exceptional circumstances.

Interest Recoverable Under a Building Liability Order

The Court also confirmed that liability under a BLO extends to interest accruing on the underlying liability. Crest Nicholson was therefore entitled to recover interest on the unpaid adjudication award in addition to the principal sum itself.

A Further Expansion of the Building Safety Act

Whilst permission to appeal was refused, the Court acknowledged the broader significance of the issues raised by the case, particularly concerning anticipatory BLOs and the interaction between adjudication liabilities and the Building Safety Act regime.

The judgment nevertheless reflects the Court’s clear view that the statutory purpose of the Building Safety Act requires a practical and commercially effective approach to enforcement and recovery.

The case is likely to become another important authority in the rapidly developing body of Building Safety Act jurisprudence and serves as a further warning that associated group entities may face substantial exposure where building safety liabilities arise within a wider corporate structure.

How CCC Can Help

At Contract & Construction Consultants (Southern) Limited, we regularly advise contractors, subcontractors, developers and consultants on adjudications, adjudication enforcements, payment disputes, insolvency-related recovery issues and claims arising under the Building Safety Act 2022.

Our team can assist with adjudication strategy, enforcement proceedings, jurisdiction challenges, contractual risk allocation and recovery options. We also advise on proactive contract administration and dispute avoidance measures aimed at reducing exposure to future claims. If you require assistance in relation to adjudication, enforcement proceedings or construction disputes generally, please contact our team for an initial consultation.

 

Contact us for a free initial consultation.

This entry was posted in News. Bookmark the permalink.

Get in touch





Related Insights

Common Causes of Construction Disputes and How to Avoid Them

Common Causes of Construction Disputes and How to Avoid Them

Why are disputes so common in construction? A job can start before the design is complete, involve input from several parties whose work depends on …

Read more
Advance Payments in Construction: Getting the Arrangements Right

Advance Payments in Construction: Getting the Arrangements Right

Be clear about what the payment is funding An advance towards a specific equipment order serves a different purpose from a payment intended to support …

Read more
Novation or Assignment? Why the Difference Matters in Construction Contracts

Novation or Assignment? Why the Difference Matters in Construction Contracts

Assignment and novation provisions are not usually the first clauses contractors or subcontractors focus on when reviewing a construction contract. But if a project changes …

Read more

Sign up for Legal Tips & Events