When an Adjudicator Goes on a “Frolic”: Premier Modular v MTW NHS Trust

10 June 2026

The Technology and Construction Court has refused to enforce an adjudicator’s decision worth over £1.6 million after finding that the adjudicator determined the dispute on a basis that neither party had advanced. In Premier Modular Ltd v Maidstone and Tunbridge Wells NHS Trust [2026] EWHC 1404 (TCC), the Court considered the limits of an adjudicator’s ability to reach their own conclusions and the circumstances in which doing so may amount to a breach of natural justice.

Background

The dispute arose under an NEC4 Option A contract for the design and construction of a new barn theatre at Maidstone Hospital. Premier Modular Ltd (“Premier”) claimed that the MTW NHS Trust (“the Trust”) failed to provide a permanent mains water supply in sufficient time for testing and commissioning activities. Premier alleged that this caused critical delay to the works and entitled it to additional time and money through the NEC compensation event mechanism. The dispute was referred to adjudication. The adjudicator found in Premier’s favour, awarding it approximately £1.65 million together with other relief. The Trust resisted enforcement of the decision, arguing that the adjudicator had breached the rules of natural justice.

The Parties’ positions

Throughout the adjudication, both parties proceeded on the basis that the only “Accepted Programme” under the NEC contract was the original programme contained within the contract documents. Although later revised programmes had been produced, it was common ground that none had been formally accepted by the Project Manager in accordance with the NEC contractual procedures. Premier’s case was that the delayed water supply gave rise to compensation events under clauses 60.1(1), 60.1(14) and 60.1(18) of the contract. The Trust denied that any such compensation event arose and further argued that any entitlement was time-barred because the relevant notification requirements had not been satisfied.

The Adjudicator’s Decision

The adjudicator rejected both parties’ analyses and concluded instead that one of the later revised programmes had effectively become an Accepted Programme, despite neither party having advanced that case and both having expressly argued the contrary during the adjudication.

On that basis, he determined that the Trust had failed to provide the water supply by the date shown in the revised programme and that a compensation event had therefore arisen under clause 60.1(3) of the NEC contract. Neither party had relied on that provision as the basis of its case.

The adjudicator therefore found in Premier’s favour on grounds that had not been advanced by either side.

The Court’s Decision

The Court refused to enforce the adjudicator’s decision. Whilst the Court acknowledged the well-established principle that adjudicators are not required simply to choose between the parties’ competing arguments, it emphasised that there are limits to that freedom.

An adjudicator is entitled to reach their own conclusions from the material before them. However, where they intend to determine a dispute on a factual or legal basis that has not been argued by either party, fairness requires that the parties be given an opportunity to address the point before a decision is made.

The Court concluded that the adjudicator had crossed that line. The decision was founded upon a contractual route to recovery that neither party had advanced and which had never been properly canvassed during the adjudication. The Trust therefore had no meaningful opportunity to respond to the case upon which it ultimately lost.

The judge described the adjudicator as effectively creating a new case for Premier and characterised this as the sort of situation where an adjudicator had gone off on a “frolic of his own”. Because that issue went to the heart of the decision, the breach of natural justice was material, and the decision could not therefore be enforced.

Why this Decision matters

The judgment serves as an important reminder of the distinction between an adjudicator making a mistake and an adjudicator acting unfairly. The courts will generally enforce adjudicators’ decisions even where there are alleged errors of fact, law or contractual interpretation. The purpose of adjudication remains “pay now, argue later”, and enforcement challenges continue to face a high threshold. However, where an adjudicator decides a dispute on a basis not advanced by either party, without giving them an opportunity to address that basis, the courts may intervene.

The case also highlights the importance of procedural fairness in NEC disputes involving compensation events, Accepted Programmes and notification provisions. Even where an adjudicator believes they have identified a better contractual route to a particular outcome, they must ensure the parties have had a fair opportunity to address it before relying upon it.

How CCC Can Help

Construction disputes often turn on detailed contractual mechanisms, notice provisions, programme obligations and entitlement under compensation event or variation procedures. A strong claim is not simply about the underlying facts but also about ensuring that the correct contractual route is identified and properly presented.

Contract & Construction Consultants (CCC) assists contractors, subcontractors, developers and employers with the preparation, defence and resolution of construction claims. Our team provides support on extension of time claims, loss and expense claims, NEC compensation events, final account disputes, adjudication proceedings and wider dispute resolution strategies. Whether pursuing or defending a claim, early contractual and procedural analysis can be critical to achieving a successful outcome.


Contact us for a free initial consultation.

This entry was posted in News. Bookmark the permalink.

Get in touch





Related Insights

Suspension for Non-Payment: Getting the Strategy Right

Suspension for Non-Payment: Getting the Strategy Right

Suspension for Non-Payment: Getting the Strategy Right Suspending construction work can be powerful leverage when payment is not made. It can also create a second …

Read more
JCT Contract Amendments: 10 Key Risks to Check Before You Sign

JCT Contract Amendments: 10 Key Risks to Check Before You Sign

A JCT contract may look familiar, but that does not mean the risk allocation is standard. The most commercially important terms are often found in …

Read more
On-Demand Performance Bonds: Why a Genuine Contract Dispute May Not Stop a Call

On-Demand Performance Bonds: Why a Genuine Contract Dispute May Not Stop a Call

On-Demand Performance Bonds: Why a Genuine Contract Dispute May Not Stop a Call A contractor may be convinced that it has a strong extension of …

Read more

Sign up for Legal Tips & Events